Lumivaara
Lumivaara is located in the municipality of Hyrynsalmi and consist of 9 wind turbines. Land use plan have been approved by the Hyrynsalmi municipality council 16 March 2016. Land use plan is legally in force.
Short-Facts
- Municipality: Hyrynsalmi
- Number of WTGs: 9
- Total height: 215 m
Download land use plan
Building permits for all wind turbines in Lumivaara legally in force
12.10.2021
Hyrynsalmi municipality has granted building permits for all wind turbines in Lumivaara. Building permits were appealed to Administrative Court and to Supreme Administrative Court. Building permits gained legal force in October 7, 2021.
Building permits for 5 wind turbines in Lumivaara legally in force
25.03.2020
Hyrynsalmi municipality granted June 19, 2019 building permits for 5 wind turbines in Lumivaara. Building permits were appealed to Administrative Court. Building permits gained legal force in March 17, 2020.
Supreme Administrative Court has rejected the appeal against Lumivaara land use plan
21.05.2019
Supreme Administrative Court has rejected 21.05.2019 the appeal against Lumivaara land use plan. Land use plan is now legally in force.
Land use plan proposal has been appealed to Supreme Administrative Court
12.03.2018
The Administrative Court of Northern Finland has rejected the Land use plan proposal appeal. The decision was made December 27, 2017. The Administrative Court decision has been appealed to the Supreme Administrative Court.
Land use plan proposal has been appealed to Administrative Court
05.02.2018
Lumivaara land use plan proposal approved by Hyrynsalmi municipal council in March 16, 2016 has been appealed to Northern Finland Administrative Court.
Land use plan proposal approved by the Hyrynsalmi municipal council
28.11.2016
Hyrynsalmi municipal council approved Lumivaara land use plan proposal March 16, 2016. Partial land use plan has been appealed to Northern Finland to the Administrative Court.